探索者的羽翼在线观看未删减完整版|人间**未删减版电影在线观看完整版|在线观看国产欧美|青在线视频,色戒电影完整版视频在线观看,芈月传电视剧全集在线观看免费版,奇米影音第四色

軟題庫(kù) 移動(dòng)APP 掃碼下載APP 隨時(shí)隨地移動(dòng)學(xué)習(xí) 培訓(xùn)課程
試卷名稱 信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-2
考試中心《信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-2》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A project manager has been collecting work performance information during the project execution phase. What is the main purpose of this action ?
A、To monitor cost, schedule progress, and deliverable status.
B、To monitor team member performance in the project.
C、To assess training requirements within the project team.
D、To update the project management plan.


相關(guān)試題

推薦文章