探索者的羽翼在线观看未删减完整版|人间**未删减版电影在线观看完整版|在线观看国产欧美|青在线视频,色戒电影完整版视频在线观看,芈月传电视剧全集在线观看免费版,奇米影音第四色

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學(xué)習(xí) 培訓(xùn)課程
試卷名稱 2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(1)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(1)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

The project manager is briefing management on project status and identifies a negative schedule variance but a positive cost variance. Which of the following conclusion is reasonable?
A、The project is behind schedule but may be brought back on schedule by adding resource
B、The project is ahead of schedule but over budget and needs further investigation
C、The project is behind schedule, over budget and merits serious concern
D、The project is ahead of schedule, under budget and progressing with no obvious issues


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容