探索者的羽翼在线观看未删减完整版|人间**未删减版电影在线观看完整版|在线观看国产欧美|青在线视频,色戒电影完整版视频在线观看,芈月传电视剧全集在线观看免费版,奇米影音第四色

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學習 培訓課程
試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(4)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(4)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內容

You are halfway through a major network rollout. There are 300 locations in the United States with another 20 in England. A software seller has just released a major software upgrade for some of the equipment being installed. The upgrade would provide the customer with functionality they requested that was not available at the time the project began. What is the BEST course of action under these circumstances?
A、Continue as planned, your customer has not requested a change.
B、Inform the customer of the upgrade and the impacts to the project's timeline and functionality.
C、Implement the change and adjust the schedule as necessary because this supports the customer's original request.
D、Implement the change to the remaining sites and continue with the schedule.


相關試題

推薦文章
合作網站內容